ADAPTATION OF BIDEGORRI DEL UROLA TUNNEL 16

Location

Zumarraga. Gipuzkoa. Spain

Name

Adaptation of Bidegorri del Urola Tunnel 16

Operation

Geotúnel

Main Details

Cleaning of vault and sidewalls - Bolting - Alternated application of shotcrete and shotcrete with Dramix type reinforcing fibre - Removal of materials to dumping site following cleaning and waste generated from the gunite process - Final cleaning

Technical Specifications air-blown concrete 350 m³ - Bolting 210 metres


We use our own and third party cookies, for the analysis of user navigation. If you continue browsing, we consider that you accept the use.
You can change the settings or get more information here.

© 2011 Grupo Moyua. All rights reserved.
Website developed by DMacroWeb using the tool DM Corporative
Share:
Info: