CONSTRUCTION OF THE GURUTXETXIKI TUNNEL

Location

Arrasate-Mondragón. Guipuzkoa. Spain

Name

Adaptation of Bidegorri del Urola Tunnel 16

Operation

Geotúnel

Main Details

Double tunnel  680.00 metres long. Excavation using blasting and mechanical methods - section type 95 m²

Technical Specifications

Excavation 128,000 m³ - air-blown concrete 4,900 m³ - Bolting 48,000 metres - Trusses 172,000 Kg