CONSTRUCTION OF THE REDONDELA TUNNEL AND UTILITY TUNNELS

Location

Redondela. Pontevedra. Galicia. Spain

Name

Construction of the Redondela Tunnel and Utility Tunnels

Operation

Geotúnel

Main Details

Bi-directional tunnel for rail traffic 2,412.00 metres long and section type of 125 m², with additional utility tunnel of 570 metres and 30 m² section

Technical Specifications Excavation 322,000 m³ - air-blown concrete 15,000 m³ - Bolting 90,000 metres - Trusses 770,000 Kg - Micropiles 29,000 metres


We use our own and third party cookies, for the analysis of user navigation. If you continue browsing, we consider that you accept the use.
You can change the settings or get more information here.

© 2011 Grupo Moyua. All rights reserved.
Website developed by DMacroWeb using the tool DM Corporative
Share:
Info: