• 3,850  M2 Pedestrian promenade
  • 270  M2 of service area on the new beach
  • 1,446  M2 of masonry stone in the vertical faces
  • 1,812  M3 of structural reinforced concrete for the retaining walls
  • 3,850  M2 pedestrian walkways
  • 270  M2 of service area on the new beach
  • Anterior
  • Siguiente
Grupo Moyua,www.moyua.com

REGULATION OF THE NEW BEACH AND SWIMMING POOL IN THE BURUMENDI AREA OF THE MUTRIKU PORT

Location

Mutriku. Biscay. Spain

Budget

€1,779,452.27

Project deadline

5 months

Name

Regulation of the New Beach and Swimming Pool in the Burumendi Area of the Mutriku Port

Client

BASQUE GOVERNMENT- Department of Public Transport and Construction

Main Details

9,320 M2 of audited area -  1,200 M2 of tidal pool - 4,270 M2 service area on the new beach - 3,850 M2 pedestrian walkways parallel to the dike access road and the outdoor area which corresponds to the swimming pool.

Technical Specifications

23,915 M3 extraction and dumping of sand for the beach and swimming pool - 8,289 M3 of causeway filling to create the platforms -  1,812 M3 of reinforced structural concrete to create the retaining walls - 72,104 kg of structural steel for the same purpose - 1,446 M2 of masonry stone in the vertical faces

 



We use our own and third party cookies, for the analysis of user navigation. If you continue browsing, we consider that you accept the use.
You can change the settings or get more information here.

© 2011 Grupo Moyua. All rights reserved.
Website developed by DMacroWeb using the tool DM Corporative
Share:
Info: