• 2,700  M2 of screen wall 80cm thick as retaining perimeter
  • 16,275  M3 of hydro-milling machine excavation up to 35 cm deep
  • 39,508  M3 of HA-30 in the main structure
  • 80,640  M3 passage excavation for site clearance
  • 35,720  M2 of solid paving with epoxide resin in floor finishes
  • 6,088  M2 of concrete cinder blocks in interior partitions
  • 47,443  M2 of paint
  • Anterior
  • Siguiente
Grupo Moyua,www.moyua.com

UNDERGROUND CAR PARK IN PLAZA CERVANTES AND SURFACE URBANISATION

Location

Donostia-San Sebastian. Guipuzcoa. Spain

Budget

€28,464,000.00

Name

Construction of the Car Park in Plaza Cervantes and Surface level Urbanisation

Project deadline

26 months

Client

Donostia-San Sebastian City Council

Main Details

8,000 M2 of constructed area over 5 underground storeys - 1,226 parking spaces - 607 short-stay parking spaces - 619 parking spaces for residents -  2,800 M2 of urbanised area - Underground Leisure Centre for people with disabilities

Technical Specifications 2,700 M2 of screen wall 80cm thick as retaining perimeter - 16,275 M3 of hydro-milling machine excavation up to 35 cm deep - 3,737 TN of steel B500S in reinforcements - 39,508 M3 of HA-30 in the main structure - 80,640 M3 passage excavation for site clearance - 10.531 M3 of excavation for piles - 643,260 KG of A-42b steel in rolled sections - 35,720 M2 of continuous paving with epoxine resin in floor finishes - 7,200 M2 of grids of hollow-core sheets - 6,088 M2 of concrete cinder blocks in interior partitions - 32,610 M2 of demolitions and dismantling of structural elements - 450 Ml of micropiles - 47,443 M2 of paint - 2,817 M2 of brick masonry in interior partitions - 8,010 M2 creation of drainage layer


We use our own and third party cookies, for the analysis of user navigation. If you continue browsing, we consider that you accept the use.
You can change the settings or get more information here.

© 2011 Grupo Moyua. All rights reserved.
Website developed by DMacroWeb using the tool DM Corporative
Share:
Info: